Back to Blog

Stage 21 Road Underway - September Newsletter

Stage 21 drainage works are complete, and construction has started on the subbase improvement layer (SIL) for the road. Service trenches are booked to be opened and our usual service providers, WEL Networks, Tuatahi First Fibre, and First Gas will be on site to install their respective services.All of the standalone sections in Stage 21 are now UNDER CONTRACT, however we still have sections available in Stages 18, 19 and 20 and high density sites available in Stages 25A, 20, and 21. For section ...

September 1, 2024

Stage 21 Progess Update - August Newsletter

Stage 21 works are progressing well, with stormwater and wastewater drainage nearing completion. Service trenches will then be opened and our usual service providers, WEL Networks, Tuatahi First Fibre, and First Gas will be on site to install their respective services. Stage 21 remains on track for titles to be issued May/June 2025. We have a range of sections for sale please see our website www.greenhillpark.co.nz/sections-for-sale/...

August 1, 2024

New Stage Release - Stage 21

Chedworth Properties is proud to release the newest stage in Greenhill Park - Stage 21.The Stage 21 sections will be easy walking access to the future town centre, and includes a variety of sites, ranging from high density sites to 397m2 sites for a large family home.Works are already underway and titles are expected May/June 2025. ...

July 15, 2024

Sections for Sale - May/June Newsletter

We have a range of sections of sections available in Stages 18, 19, 20 and 25A. These range from development blocks, to 210m2 extra small lots (that will fit a 3 bedroom home with a garage), to 375m2 sites perfect for a 4+ bedroom home.Stage 18 – 9 sections leftStage 19 – 2 sections leftStage 20 – 14 sections left + 1 development blockStage 25A – 3x development blocks available...

May 1, 2024

Greenhill Open Day - April Newsletter

The Greenhill Park show home open day marketing is live and generating a good amount of interest. The marketing includes:A Facebook event, Facebook post and Instagram post with over 50,000 impressions to date, and over 120 people showing as either attending or interested.A half page in the NZ Herald booked to go out this weekA full page in the Waikato Herald Property GuideRadio advertising on the The Breeze, The Edge and Magic FM. All currently live.Thanks to all the builders who have helped wit...

April 1, 2024

Strong Start to 2024 - March Newsletter

Sales have been strong in Greenhill Park in the start of 2024 with builders purchasing 23 sections, and individuals showing increased interest. The updated sales tables for Stage 18, 19 and 20 are shown below, with the ORANGE representing SOLD sites and PINK showing sites currently under contract (3). Sites available are shown in GREEN. These tables can be viewed on our website www.greenhillpark.co.nz/sections...

March 1, 2024

Neighbourhood Centre - February Newsletter

We have created a dedicated webpage to the upcoming neighbourhood centre, which can be found via the link below. https://www.greenhillpark.co.nz/neighbourhood-centre/...

February 1, 2024

Stage 20 Completed - January Newsletter

Stage 20 works are now fully complete with the final Council walkover undertaken on 23 Jan. The project has been completed well ahead of schedule, so looking very good for titles to be issued in May 2024 if not earlier. We have sections available in Stage 20 please see our website https://www.greenhillpark.co.nz/sections/...

January 1, 2024

Neighbourhood Construction - December Newsletter

Work has started on the design for Greenhill Park’s Neighbourhood Centre. The Neighbourhood Centre will be made up of a childcare centre, a bar/restaurant, a small supermarket, a medical centre, a pharmacy, along with retail spaces for coffee, hairdressers etc. The Neighborhood Centre will be easily walkable from all sites within Greenhill Park, and will be in very close proximity to the current sites we have for sale in Stages 18, 19, 20 and 25A. The concept plan...

December 1, 2023

Stage 20 Nearly Complete - November Newsletter

Stage 20 is practically complete with only asphalt remaining to be laid, which is booked for Monday 4 December. From there we will be undertaking the final walkover with Council and lodging the works clearance application. At this stage the project is ahead of schedule, so looking very good for titles to be issued in May 2024 if not earlier....

November 1, 2023

Webb Drive Construction Planned - October Newsletter

Concrete is complete, roading basecourse is complete, streetlights are up, landscaping is completed, and the sites are topsoiled. Stage 20 is therefore now completed other than the road sealing which is booked in for December 2023. At this stage the project is ahead of schedule, so looking very good for titles to be issued in May 2024 if not earlier....

October 1, 2023

Stage 20 Progress - September Newsletter

Concrete is nearing completion in Stage 20 and streetlights are now up. Power boxes are being installed over the next few weeks, and planting is also booked to commence shortly. At this stage the project is ahead of schedule, so looking very good for titles to be issued in May 2024 if not earlier....

September 1, 2023

Stage 20 Progress - August Newsletter

Stage 20 continues to progress with drainage, services and basecourse all completed. The concrete works are well underway with around 75% of the footpaths and carparks now poured. Following the completion of concrete final work on the road will commence. At this stage the project is ahead of schedule, so looking very good for titles to be issued in May 2024 if not earlier....

August 1, 2023

3 Stages Completed - July Newsletter

Webb Drive currently runs from Pardoa Boulevard to Carrs Road. This will eventually extend to the Waikato University and complete the “Spine Road” through Ruakura. Chedworth Properties has started the engineering design process for the remainder of Webb Drive through Greenhill Park to the southern boundary of the development. As part of the construction of Webb Drive, a new stormwater swale network will be constructed including Swales 5, 6A and 6B. Swales 3 (see imag...

July 1, 2023

Recognised by Executive Leaders - June Newsletter

Recently HCC took a group of executive leaders from high growth councils – Tauranga City Council and Queenstown Lakes District Council – on a short-notice informal bus tour through the central city. We were very happy to receive the feedback below from HCC following this tour - On the day there was significant flooding right throughout Hamilton and we drove the bus through much of this, however there was no flooding at Greenhill Park.The focus on stormwater swales and public o...

June 1, 2023

Stage 18&19 Titles Issued - May Newsletter

Stage 18 is completed with Titles issued 13 April 2023. Stage 19 has received S223/224C from Council and the titles were lodged to LINZ on 17 May 2023. Based on the current processing timeframes with LINZ, titles for Stage 19 are expected mid June 2023, with settlements being due late June 2023. The following documents are now available for both stages to assist with you Building Consent applications.Geotechnical Completion ReportServices As Built PlansDraft LT Plan...

May 1, 2023

Stage 18&19 Completed - April Newsletter

Stage 18 is completed with Titles issued 13 April 2023. Stage 19 is now practically complete on site, and Works Clearance has been APPROVED by Council. The S223/S224C applications were lodged to Council on 27 April 2023 and will be issued by 12 June 2023. Based on the current processing timeframes from Council and LINZ, titles for Stage 19 are expected June 2023, with settlements being due late June 2023. The following documents are now available for both stage...

April 1, 2023

Stage 18 Completed - March Newsletter

Stage 18 is complete and the s223 and s224C applications have been granted. Titles were applied for through LINZ on the 6th of March, and are expected to be released early April 2023. With titles imminent, now is a great time to consult with your solicitor to facilitate settlement(s). The following documents are now available to assist with you Building Consent applications.Geotechnical Completion ReportServices As Built PlansDraft LT PlanCouncil approved street numbersP...

March 1, 2023

Stage 18 Nearly Complete - February Newsletter

Stage 18 is now practically complete on site with Works Clearance approved by Council. The s223 and s224C applications have been lodged and are expected to be approved this week, meaning we will be lodging for titles with LINZ in early March 2023. Stage 18 titles are therefore expected to be released early April 2023.The following documents are now available to assist with you Building Consent applications. Geotechnical Completion ReportServices As Built PlansDraft ...

February 1, 2023

Welcome to Greenhill Park - January Newsletter

Welcome the first Greenhill Park Newsletter of 2023. We hope that you had a relaxing Christmas break with family and friends, and managed to find some nice weather along the way! The team here at Chedworth Properties is looking forward to a busy 2023 with the completion of Stages 18, 19 and 25A, construction starting on Stage 20, and plenty of other exciting projects in the pipeline for this year....

January 1, 2023 Posts 1-20 of 20 | Page