Work has started on the design for Greenhill Park’s Neighbourhood Centre. The Neighbourhood Centre will be made up of a childcare centre, a bar/restaurant, a small supermarket, a medical centre, a pharmacy, along with retail spaces for coffee, hairdressers etc. The Neighborhood Centre will be easily walkable from all sites within Greenhill Park, and will be in very close proximity to the current sites we have for sale in Stages 18, 19, 20 and 25A. The concept plans can be viewed via the link below.

https://www.dropbox.com/scl/fi/ffj7h66em6qy5qhdtn0kk/Greenhill-Park-Neighbourhood-centre-concept-package-reduced.pdf?rlkey=4xxjrbwjqox643u8tqhun9d0z&dl=0

We plan to commence with detailed design and consenting in 2024, with construction work on the first stage likely to get underway in 2025/26.

Stage 20

Stage 20 works are now fully complete with the asphalt laid. The project has been completed well ahead of schedule, so looking very good for titles to be issued in May 2024 if not earlier.

Webb Drive Extension Construction

Webb Drive extension construction is underway with the establishment works, erosion and sediment controls in place, the stripping of the road completed and stormwater and wastewater drainage underway.

Key Dates

  • Stage 25A – Practically complete. Titles available ~1 month from purchase.

  • Stage 20 – Practically complete. Tiles anticipated in May 2024.

  • Webb Drive extension – Works underway and expected to be completed in late 2024

  • Greenhill Park Neighborhood Centre – Consenting work will be undertaken over 2024 and construction on Stage 1 expected to commence 2025/26.

Contact Greenhill Park

We have a range of sections available from large sites that would suit a single dwelling, to high density lots. To view available sites visit https://www.greenhillpark.co.nz/sections/ or get in touch with Brendon on 0800 639 929, or email info@greenhillpark.co.nz